Independent customer review. Not affiliated with, sponsored by or endorsed by L&G Building & Concrete. How this site is sourced

LG Building & Concrete Review

What L&G Building & Concrete charged, line by line

If you are pricing a metal building, real numbers are hard to find. These are mine, from contract ODR-001094, signed in February 2026 for a site in western North Carolina.

The building: $50,551

Company statement: L&G sales order, February 12, 2026

A certified 50 ft × 80 ft × 16 ft vertical-roof building in 14-gauge framing, dark gray sides with glossy black roof, trim and wainscot, plus a 12×35 lean-to on the right and a 12×50 lean-to across the back. “Certified” means it comes with engineered drawings meant to pass county inspection.

QtyItemList price
150×80 vertical roof building (roof 81 ft, 14 gauge, 3/12 pitch)$36,300
116 ft height (ladder legs baserail)$8,400
1Other certification (including lean-tos)$0
2Ends, closed, vertical$9,420
2Sides, closed, vertical$8,060
1Right lean-to 12×35 (wrapped length 47 ft, 2/12 pitch)$5,050
1Right lean-to, 13 ft height$820
1Right lean-to, front certified gable$375
1Right lean-to, side closed$1,775
1Back lean-to 12×50 (wrapped length 62 ft, 2/12 pitch)$6,600
1Back lean-to, 13 ft height$1,090
1Back lean-to, back certified gable$375
1Back lean-to, side closed$2,267.50
3Front 24×36 in. windows, black with grid$690
3Back 24×36 in. windows, black with grid$690
2Right side 36×80 in. walk-in doors, 9-lite, black$1,320
2Right side 14×14 ft garage door frame-outs$1,200
1Right side 10×10 ft garage door frame-out$400
4Back lean-to 14×12 ft garage door frame-outs$2,400
3Right lean-to 14×12 ft garage door frame-outs$1,800
1Site-specific blueprints, 4 ft centers$3,000
17k telehandler lift (customer provided)$0
1Generator fee$150
1Soffit, wainscot, J-trim, ladder-leg baserail (listed as free)$0
List prices added up$92,182.50
“Manufacturer discount”$41,631.50
Building total, no sales tax charged$50,551

Notice how the price is built. The line items add up to $92,182.50, and then a single “manufacturer discount” of $41,631.50 takes off about 45%. The number that matters is the bottom one. When you compare quotes between metal-building sellers, compare bottom lines and ignore the size of anybody’s discount.

Also notice the $0 lines. “7k Telehandler Lift (customer Provided)” means the machine that lifts the trusses was mine to rent and have on site. A $0 on the order form did not mean the lift was free. It meant the cost was on me and outside the contract.

The concrete: $48,199

ItemWhat the contract specifiesPrice
Pad size50 ft 7 in. × 80 ft 7 in. main pad, plus a 12×47 ft and a 12×62 ft lean-to pad$37,380
Pad thickness6 in. under the building, 4 in. under each lean-to
Concrete strength3,500 psi
GradingYes, up to 2 hours. $150 for each additional hour$1,000
Footers1×1 footers, a 47 ft strip footer and a 62 ft strip footer. “Inspection required”$9,594
Vapor barrier6 mil$225
CertifiedYes, “inspection required”
FinishLight broom finish selected
Concrete total$48,199

The three pads come to about 5,384 square feet, so the pad price works out to roughly $6.94 a square foot before footers and grading, and about $8.95 a square foot all in. L&G’s standard slab is 4 inches at 3,000 psi. My contract specifies more than that: 6 inches under the building, at 3,500 psi. I paid for that specification, which is why the thickness of what actually got poured matters to me.

The concrete sheet I signed says there is no warranty on any of it. Read the clause.

When the money is due

WhenForAmount
At signingBuilding deposit (38.97% of the building price), by bank wire$19,700
When the concrete crew arrivesFooters and grading$10,594
When concrete is scheduledConcrete balance, before the pour$37,605
When the building is scheduledBuilding materials, before delivery$22,283
When the building is completeInstallation$8,568
Grand total for the project$98,750

Add up the first four rows and you get $90,182, which is 91% of the project, due before the building is complete. Only the last $8,568 waits for completion. All of it moves by bank wire, which cannot be reversed. On top of the schedule sit the extras the contract allows: $150 an hour for grading beyond two hours, $300 return-trip fees, and any additional concrete and labor if an inspector wants deeper footings.

I have paid about $93,000 so far. The schedule calls for $90,182 before completion. On top of that I was charged for two things that are on none of my signed paperwork: extra money to correct footings that were dug to 12 inches when the plans called for 14, and a concrete pump. A payment ledger with dates and wire confirmations is being assembled and will replace this paragraph.

How I would structure the payments if I were doing it again